In the CMAA Agency series, can the Designer object to the Construction Management Plan prepared by the CM?

Prepare for the Construction Manager-in-Training exam with engaging quizzes. Master the essentials with multiple choice questions and detailed explanations. Achieve success in your exam!

The correct answer is that the Designer is entitled to object to the Construction Management Plan prepared by the Construction Manager (CM). This is an important aspect of collaboration in construction projects, where multiple stakeholders have a role in reviewing plans and ensuring alignment with the project's goals and standards.

The Designer’s ability to object is rooted in their responsibility to ensure that the design intent is maintained throughout the construction process. If the Construction Management Plan conflicts with the design specifications or could lead to issues that affect the functionality, safety, or aesthetics of the project, the Designer has the right to raise concerns. This objection can foster a team-oriented environment and improve the final outcome by prompting discussions that might lead to adjustments in the plan that better accommodate the design.

Maintaining communication and allowing for objections ensures that the voices of all key players are heard, contributing to a more thorough review process and ultimately a more successful project. This collaborative approach is fundamental in construction management, emphasizing that each team member plays a critical role in the project's success.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy